Franklin High School


Franklin High School

Project: Franklin High School Roof Replacement

Location: Seattle, WA 98144

General Contractor: Wayne’s Roofing, Inc.

Owner of the Building: Seattle Public Schools

Estimated Timeframe: 5 months

Public/Private/Federal: Public

Consisting of the following:

  • Approximately 35,000 sq. ft., complete tear-off with APP 3-Ply & Standing Seam Steel Reroof

  • Extensive seismic upgrading to include 1-1/8” T&G plywood diaphragm with metal strapping at main gym and substantial seismic steel bracing at interior of auxiliary gym

  • Project included a substantial amount of masonry work, including addition of helical ties and steel angle ledgers

  • Project topography and building placement required use of portable crane for safety & efficiency